Glulam columns and cross-laminated timber floors can now hold up 14 office levels in Melbourne’s Cremorne, with Victoria approving a 57.9-metre design on a site where local controls preferred 28 metres. That is according to Victoria’s Department of Transport and Planning, whose officers recommended the permit before the Minister for Planning issued it last Wednesday.
“It is not considered necessary to implement these design changes,” the department’s officer report states of Yarra City Council’s call to cut five storeys. Endor Development must instead trim the floor-to-floor heights and rooftop screen, after sketch plans it submitted in mid-October showed “modest reductions” may be achievable.
Yarra City Council had argued the scale of the building failed to recognise the pattern of development and character of Stephenson Street. Objectors lodged six objections over its height, its bulk, and the precedent it would set for Cremorne.

By contrast, officers found the site has no mandatory height limit, and noted approvals for buildings of 9 to 13 storeys elsewhere in Cremorne. Their own urban designers called the building “architecturally sophisticated”, but wanted it lower to sit better against Stephenson Street.
Officers judged the building’s public benefits outweighed its departure from the height controls. Those benefits include at least 500 square metres of workspace for a not-for-profit tenant at peppercorn rent for 10 years.
Meanwhile, rail land manager VicTrack backed the building, whilst Transport for Victoria set conditions from reflected sunlight to train radio coverage. The building also cannot rely on the railway land, or the air above it, for light, ventilation, or fire safety.
Large projects like this one go to the minister rather than the council under the state’s Development Facilitation Program. Department officers recorded a development value of $68 million for the office and its 13,145 square metres of lettable space.

Endor also has a year from occupation to prove a 6 Star Green Star rating, 4 star NABERS embodied carbon, and Passivhaus certification. The Office of the Victorian Government Architect said none of those goals was new on its own, but together they “would constitute Australian leadership”.
“The process of self-extinction is defined as the cessation of flaming,” Carbon Fire Engineering states in the design advice letter James O’Neill prepared for Endor. Edition Office’s design leaves the timber exposed at more than twice the height Australia’s standard fire rules allow in wood, as Wood Central reported.

As it stands, work must start within three years and finish within five, or the permit expires. Plans showing the lower height must be approved before construction moves beyond demolition, excavation, and piling.
Vettex director Chris Coyle, Endor’s project manager, said before the decision that Victoria’s fire authority had been cautious about buildings of this scale. He put that down to fire engineering on earlier Melbourne mass timber proposals failing scrutiny, and said Carbon Fire’s brief should change the outcome.
The Daily Digest