A finished mass timber frame now stands on the Hastings site of a council office block that staff vacated over earthquake risk six years ago, with delegates at WoodWorks 2026 walking through it last Thursday. It comes after Wellington builder LT McGuinness completed the four-storey structure in 59 working days, which it put down to a model-first approach and its suppliers Red Stag and TimberSpan.
“One of the things that has really stood out is how incredibly quiet the site has been throughout the timber installation,” said Tumu Property project manager Ben Hamelink. Hamelink said Heretaunga House, as the new building is known, took 1,000 cubic metres of Red Stag TimberLab cross-laminated timber and 400 cubic metres of TimberSpan laminated veneer lumber.
Ben Hamelink’s timelapse shows Heretaunga House’s mass timber frame going up in central Hastings, through to topping out. (Post courtesy of Ben Hamelink)
By the halfway mark, the team had installed 2,800 square metres of floor area in just 24 working days, he said. When the final roof panel went in, 44,000 Rothoblaas screws were holding the frame together, with the job running ahead of schedule.
That speed was on show last Thursday, with Heretaunga House the first site visit at WoodWorks 2026, a conference that counted Red Stag TimberLab and TimberSpan among its partners. Delegates toured the frame hours after PEFC International’s Richard Laity urged specifiers to stop naming just one certification system, before heading on to Te Aka, Napier’s new library.

It comes as Mark Ross, chief executive of the Wood Processors and Manufacturers Association, called Heretaunga House “a great example of what can be achieved with mass timber builds.” Ross said association members Red Stag TimberLab and Nelson Pine both hold FSC rather than PEFC certification, and that he understood Nelson Pine supplied TimberSpan’s laminated veneer lumber.
Heretaunga House takes its name from the block that stood there before, a three-storey council office that Prime Minister Robert Muldoon opened in 1983 on the corner of Warren Street and Lyndon Road. Council staff and tenants moved out after seismic assessments found it fell short of the New Building Standard, with councillors approving its deconstruction in 2021.
Earlier this year, Wood Central reported that the council had sold the cleared site to Tumu for NZ$2.5 million and would lease back 1,950 square metres for $830,000 a year. The council said it chose the sale-and-leaseback as the most cost-effective option for ratepayers, because private business would fund the office without the council needing to invest.
“We are getting an efficient, fit-for-purpose base for our team,” said Hastings mayor Sandra Hazlehurst, who called the development a win-win for the city. Once the building opens, those 80 staff will work from one central office, whilst Tumu takes 600 square metres for its own headquarters.
TimberSpan is “the strong, sustainable skeleton of the building,” according to Tumu director Hamish Frame, who has described it as the company’s “locally manufactured mass timber system.” Tumu has said it chose LT McGuinness as main contractor for its experience with mass timber, whilst Hamelink has praised the “passionate local contractors working alongside the experienced operators” from the Wellington builder.
LT McGuinness marks the completion of Heretaunga House’s mass timber structure in 59 working days, from the first CLT core panel to the final CLT roof panel. (Post courtesy of LT McGuinness)
“The structure may be complete, but the journey continues as we move into the next exciting phase of the project,” LT McGuinness said after topping out. As it stands, the builder said façade construction and interior trades had begun, whilst Tumu is leasing the rest of the building’s office space to commercial tenants.