* Advertisement *
20260420 WC 900x130

King Charles Housing Project Proves Australia Needs a CLT Standard

The $65 million Cowper Street redevelopment, backed by The King's Trust Australia, delivers NSW's first mass timber social housing and Australia's first fully electrified, 6-Star Green Star social homes. Its architect says a national CLT standard must come next.


Mon 13 July 26

SHARE

The Cowper Street redevelopment is fit for a king, yet the architect behind NSW’s first mass timber social housing warns that without a national CLT standard, Australia will struggle to build another. That is according to Noura Thaha from GroupGSA, who used a Fifth Estate Project Files contribution this week to reveal that every element of the $65 million Glebe project had to be separately justified through costly Performance Solutions.

“Exceptional clients, exceptional risk tolerance, and exceptional fees,” Thaha said, cannot remain the price of admission for timber social housing, with the National Construction Code offering no straightforward Deemed-to-Satisfy pathway for exposed CLT in Class 2 apartments. Instead, she wants nationally accessible guidelines and publicly available fire testing so project teams stop paying to solve the same problems twice.

Eighteen months before residents began moving in, King Charles III toured the half-built towers to unveil a commemorative plaque on the boldest Australian project backed by his own trust. Wood Central understands the development began life in 2022 as The Prince’s Quarter, announced with the then Prince’s Trust Australia, before the charity was renamed following the King’s accession.

“Cowper Street shows how good design can help deliver more homes in established communities,” Rebecca Pinkstone, the Homes NSW chief executive, said after the project reached completion. According to Pinkstone, the finished buildings, the first fully electrified and first 6-Star Green Star social housing in Australia, improve quality and amenity while respecting the character of Glebe.

King Charles III unveiling a plaque at the Cowper Street Glebe construction site in October 2024 with Anthony Albanese and Chris Minns applauding
King Charles III unveils a commemorative plaque during his October 2024 visit to the Cowper Street social housing site in Glebe. (Photo Credit: Previously supplied to Wood Central)

Officially opened on 26 March with residents moving in from April, the $65 million project for Homes NSW, The King’s Trust Australia and Bridge Housing swaps 19 ageing dwellings for 75 new social homes and 130 tenants, a near-300 per cent uplift on the old estate. Kane Constructions built the towers around CLT and glulam pressed by XLam, with three studios, 40 one-bedroom and 27 two-bedroom apartments across the pair, plus five three-bedroom terraces fronting MJ Doherty Reserve.

First unveiled by Johnson Pilton Walker in 2020, the concept was billed as Sydney’s boldest public housing project in decades, only to be converted from a mixed-tenure scheme to entirely social housing after DA approval. Several more amendments followed to make the switch to mass timber possible.

XLam pressed all 2,590 cubic metres of the project’s CLT and glulam at its Wodonga plant, using pine grown in NSW State Forests. Every floor plate and internal wall above the Level 1 concrete transfer, except the lift core, was constructed in cross-laminated timber and left exposed in the apartments as feature walls.

Resident on the balcony of a Glebe social housing apartment with an exposed cross-laminated timber feature wall
Inside the apartments, XLam’s cross-laminated timber is left exposed as feature walls, with the brick veneer beyond. (Photo Credit: Alicia Taylor, courtesy JPW and ArchitectureAU)

Figures unveiled at the project’s topping out put the structure’s stored carbon at 1,860 tonnes, the equivalent of taking 934 cars off the road for a year. Speed was the payoff, with floors on the eight-storey towers raised in as little as a fortnight and the three-storey terraces completed in three weeks.

But the decision to wrap the towers in a traditional brick skin, chosen to sit alongside Glebe’s historic terraces, significantly slowed the program. Bricklaying took three to four weeks per level and could only start once the CLT was complete, leaving the timber unprotected and pushing completion from early 2025 into early 2026.

According to Thaha, a prefabricated facade could have halved that time or been built almost floor for floor with timber. Instead, the team blended dry-pressed and extruded bricks, easing the call on bricklayers and improving cavity ventilation.

“A showcase of traditional architectural approaches,” is how JPW director Graeme Dix described the finished towers, arguing the brick detailing responds to the woolstores, warehouses and dense terraces that surround them. Tripling the homes on site, Dix said, proves density can be done well in even Sydney’s most crowded suburbs.

Red brick facade with arched openings on the Cowper Street social housing tower beside a cream brick building in Glebe
Herringbone brick detailing on the Cowper Street towers responds to the woolstores and Victorian terraces that define Glebe. (Photo Credit: Alicia Taylor, courtesy JPW and ArchitectureAU)

As one of the first projects of its type in the state, research alone consumed nearly 70 per cent of the design workload. With almost nothing published on CLT in Class 2 buildings, the team modelled the towers to LOD 400 and ran Navisworks clash detection across every junction and penetration, down to individual bricks.

Costs have long been the obstacle, with GroupGSA noting “a lack of shared IP across the construction industry” stood between architects and Class 2 timber buildings for years. The surprise, Thaha said, was that CLT proved more forgiving than concrete once mastered, offering looser tolerances and cleaner service penetrations without the reinforcement clashes that complicate concrete documentation.

Kane Constructions XLam and Kings Trust representatives holding a topping out plaque against an exposed CLT wall at Cowper Street
: Project partners mark the topping out of the Cowper Street towers, where 2,590 cubic metres of locally grown pine now stores 1,860 tonnes of carbon. (Photo Credit: Photo previously supplied to Wood Central in 2024 by Xlam Australia)

Classified as Type A construction, the highest fire-resistance tier in the NCC, the project ran headlong into a familiar problem: Australia still has no dedicated CLT standard, and regulators continue to classify engineered timber as combustible. Decades of international evidence show CLT chars predictably under fire, sacrificing their outer layer to insulate the structure beneath, a behaviour many engineers regard as more predictable than steel.

Australia’s Deemed-to-Satisfy pathway for fire-protected timber, introduced in 2016 for sprinklered buildings up to 25 metres and extended in 2019 to schools, retail, hospitals and aged care, generally demands the timber be encapsulated behind fire-grade plasterboard. That pathway did not cover the exposed CLT at the heart of the Glebe design, leaving the project reliant on Performance Solutions built from British Standards and overseas precedents, alongside privately held technical documentation accessed at a cost.

Australia’s humid, wet climate added further complexity, with regulatory pressure to wrap timber in fire-rated linings working directly against the material’s need to breathe. Conditions could not be further from the cold, dry European markets where CLT was pioneered.

CLT panel burn test underway at CSIRO North Ryde Fire Technology Laboratory with flames across the underside of a suspended floor assembly
A CLT panel burn test at CSIRO’s North Ryde Fire Technology Laboratory, which will shut in December in a 50 per cent hit to Australia’s fire testing capacity, as Wood Central exclusively revealed in May. (Photo Credit: Supplied to Wood Central / Central PR Group)

Thaha’s call for publicly available testing comes as CSIRO prepares to close its North Ryde Fire Technology Laboratory when its lease expires in December, removing up to half of the country’s NATA-accredited large-scale fire-testing capacity. Industry sources had previously warned Wood Central that compliance assessments, already running for 2 years, could stretch to 4 or 5 years.

“It is the loss of nationally significant innovation infrastructure,” Simon Croft, the Housing Industry Association’s chief executive for industry and policy, said last week, warning that every engineered timber product and prefabricated system must pass rigorous testing before the industry can adopt it at scale.

While Glebe’s panels came from Australian-grown radiata pine, Thaha noted that national manufacturing capacity remains thin, to the point that trucking timber across the country can produce more carbon than importing finished CLT panels. The shortfall echoes the Sydney Fish Market’s showpiece roof, fabricated in Italy because no Australian plant could press it.

For now, Glebe stands as the strongest proof yet that timber social housing works in Australia, and the precedent every future Class 2 CLT project will build on, with NSW facing a 377,000-home shortfall that prefabrication is expected to help close. Repeating it at scale hinges on what replaces North Ryde when the doors shut in December.

Author

  • J Ross headshot

    Jason Ross, publisher, is a 15-year professional in building and construction, connecting with more than 400 specifiers. A Gottstein Fellowship recipient, he is passionate about growing the market for wood-based information. Jason is Wood Central's in-house emcee and is available for corporate host and MC services.

    View all posts

Related Articles