New Rig to Test Shadows at Cricket’s Largest Timber-Roofed Stadium

Past and current cricketers will this week put a matte roof treatment to the test — the first physical trial of a fix that could decide cricket's future at Mac Point


Tue 10 Mar 26

SHARE

Past and current cricketers will this week begin testing a physical rig at Hobart’s Macquarie Point — the first real-world trial of a proposed fix to the shadow problems threatening the $1.13 billion stadium’s cricket future beneath its glulam timber-framed roof.

That is according to Pulse Tasmania, which reports the rig is designed to replicate the planned venue’s fixed-roof structure and will assess whether a treated version of the stadium’s ETFE roof material can eliminate the shadow problem that has dogged the project since early 2025.

Shadows have plagued the design from the beginning.

Last year, Wood Central reported that Cricket Australia and Cricket Tasmania wrote to the Tasmanian government demanding architects redesign or remove the roof entirely, saying the fixed-dome design made the venue “unlikely to be conducive to hosting Test matches” — and potentially unworkable for one-day and T20 fixtures too.

At the time, Anne Beach, the CEO of the Macquarie Point Development Corporation, told a parliamentary inquiry that the transparent covering created contrast on clear days — and that the timber and steel beams, engineered as small as possible, would still cast shadows.

However, in November, a Gold Coast company identified a potential fix: Cricket Tasmania CEO Dom Baker proposed a matte treatment that, when applied to one side of the ETFE material, would disperse light rather than pass straight through —  killing the sharp contrasts on the pitch.

Until this week, it had never been physically tested. Now, the rig will run assessments on shadow intensity, ball visibility, and playing conditions. It will also capture data on how roof treatments affect turf growth beneath — a secondary concern for groundskeepers at an indoor venue.

It comes after both houses of the Tasmanian Parliament approved the $1.13 billion project in December — the Upper House voting 9–5 after two days of debate. The 23,000-seat venue will be the permanent home of the Tasmania Devils AFL team. Its fixed dome, framed in Tasmanian-sourced glulam, would be the largest timber roof on any stadium in the world.

What the roof actually looks like

Late last year, Wood Central reported that the current design documents detail a hybrid timber roof lined with Tasmanian-sourced glulam, paired with metal deck cladding, steel rod bracing, and translucent ETFE pillows. The clearspan structure carries an internal clearance of 49 metres — enough headroom for Test-level cricket as well as AFL, soccer, and rugby.

The Macquarie Point Summary Report specifies lightweight ETFE pillows, a 20-millimetre timber laminate, a secondary glulam system, and Aramax metal deck cladding, all supported by steel rod bracing. The timber form is designed to reduce perceived bulk from street level and preserve harbour sightlines — a tough ask for a structure sitting on the edge of Hobart’s CBD.

Author

  • J Ross headshot

    Jason Ross, publisher, is a 15-year professional in building and construction, connecting with more than 400 specifiers. A Gottstein Fellowship recipient, he is passionate about growing the market for wood-based information. Jason is Wood Central's in-house emcee and is available for corporate host and MC services.

    View all posts
- Advertisement -spot_img
- Advertisement -spot_img

Related Articles